NY’s data center freeze adds a new risk for AI investors: State regulation

A one-year pause on data center permitting makes New York state the first to enact a moratorium.

New York Gov. Kathy Hochul’s immediate, one-year moratorium on new data center construction, via an executive order on Tuesday, introduced an unexpected hurdle into the fast-growing business of building AI data centers.

Hochul’s move—which makes New York the first state to block data center construction—has private market investors reassessing plans and sizing up potential downstream effects. The moratorium also comes as public opinion has turned staunchly against data centers, with Americans expressing concerns about noise and pollution, as well as rising electricity and water costs.

For AI infrastructure companies, pivoting to another state for new data center construction comes with its non-trivial complications, said Ted Brandt, founder and CEO of investment bank Marathon Capital. Even red states have responded to the growing public outcry: Texas Gov. Greg Abbott recently called for a ban on data centers in rural parts of the state, and previously unveiled a new regulatory framework aimed at limiting their resource impact.

“It’s not at all clear which states are going to be data center central,” said Brandt, whose firm specializes in renewable energy and infrastructure deals, including data centers. “It’s an open question. And when you’re starting to see New York and Texas on the same side of an issue, it’s an extraordinarily weird situation.”

Sign up for The Daily Pitch newsletter

More recently, data centers and the electricity needed to power them have become the new hurdle for the AI industry.

“The bottleneck stopped being chips a while ago,” said PitchBook senior analyst Harrison Rolfes. “New York didn’t create that scarcity—it converted the constraint from a physics problem into a political one. Transformers and interconnection queues: Capital can eventually engineer around [that]. Permits and a governor’s signature, it can’t.”

Of the roughly 241 gigawatts of US data center capacity in the pipeline by the end of 2025, only about a third is under active development, according to research firm Wood Mackenzie—the rest has stalled largely due to power constraints. The York executive order puts a one-year moratorium on the state approving permits for new data center construction exceeding 50 megawatts of capacity.

Data center deal value, dominated by PE investment, hit a five-year high of $48.1 billion in 2025, according to PitchBook data.

A May Gallup poll found that 71% of Americans oppose a data center being built near them, outpacing the 53% of Americans who oppose a new nuclear power plant in their backyard. A Pew Research survey in January found more Americans saying that data centers are more bad than good for the environment, home energy costs and quality of life nearby.

“Data center development threatens to hike up utility bills, deplete our natural resources, and create uncertainty for New Yorkers,” Hochul said in a statement accompanying her executive order, which cites the strain data centers place on New York’s power grid, as well as the state’s water system. There are nearly 12 gigawatts of data center load requests, with more than 8 gigawatts added in 2025 alone, the state said. A similar measure passed by the state legislature in June had not yet been sent to Hochul for her signature.

The key due diligence question emerging for VC and PE investors is the regulatory risk AI infrastructure companies face, according to Rolfes and Brandt.

“The headline is a ban,” Rolfes said. “The actual event is that ‘time-to-power’ just became a valuable commodity in the AI stack. A state legislature, not a chip shortage, is now setting the price.”